Tuesday, January 31, 2012

January 2012 Update

The New Year has brought about much change at Forrester.  The installation of the brick for all buildings is about 85% complete and the installation of the siding is about 70% complete.  We've also started pouring the sidewalks and walking trails, these amenities are about 80% complete.  Plumbing and electrical rough ins are 100% complete.  The drywall has been delivered and awaiting install.

Check out some of the latest pictures from the construction site and, as always, please leave comments on this blog or contact us via email (forrestersenior@gmail.com) with any comments or concerns you may have.