Saturday, March 31, 2012

March 2012 Update

Construction is still progressing quickly!  All of the exterior painting is complete (with the exception of building 70).  The interior painting work is 85% complete in each building.  Plumbing fixtures the HVAC systems are in the process of being installed.  Kitchen applicanes are next....

The landscaping is nearing completion and looking good.

The property is starting to look like the vision we had for it when we began planning the development in late 2009.